Work carried out this week was:-
On the 4th and 5th floors, the drylining, including sound insulation and the resilient bars have continued to be fitted.
M&E to the new apartments continuing. Bathrooms now with most first fix plumbing. Electrical first fix wiring and AV wiring being run.
Flat roof areas continued having the first layer of waterproofing fitted. Second layer fitted in most places.
The stone fitting to the front continued with the stone panels being fitted.
Windows the the new 4th floor with glass now fitted.
The Knight Frank rear extension had the roof structure fitted.
Air conditioning started to be fitted with the cassettes fitted above the ceilings in places.
Plastered more of the walls and ceilings in the new Flats.
Applied some of the exterior STO insulation to the rear walls. This is a non-flammable ‘Rockwool’ type material.
Stainless steel roof continuing.
New stainless steel roof over the new tank room at the rear was fitted.
Work to be carried out next week;
The stone to the front elevation will continue to be fitted to the framing this coming week. The stone is fixed on metal rails which are bolted to the concrete panels. Noise will continue but it is more ‘drilling’ type noise and not hammering with heavy machines type noise. This work is crucial to getting the scaffold down. Between the stone panels is fire barrier called ‘siderise’.
Insulation to the rear walls will continue to be fitted.
Internal work within the new Flats will increase and to include further plastering and fitting of bathrooms. Walls will be closed and plumbing and electrics will advance.
Flat roof finishes to continue.
Air conditioning and ventilation works will continue in the new Flats.
Stainless steel roof to the main building will continue.
Currently, the start date for scaffold coming down is still around the end of March. It will take around 4 weeks so we can expect all scaffold to be gone by the end of April.

New 4th floor with windows in and plastering progressing.

New roof areas to the south. These are to be covered with a sedum roof.

Non-flammable insulation board being fitted to the rear elevations.

Starting to fix the stone panels to the front. This is the Moleanos lighter stone. The second stone is Jura, a darker material.

New rear extension to the Knight Frank unit.

Siderise fire barriers.

Front terrace area being completed. This area will have decking.

Front terrace area being completed.

Natural stone panels to the front now advancing well.

Stainless steel roof to the new rear tank room.