Update of 21 July 2023
22 July 2023 356
Update of 21 July 2023
Work carried out this week was :-
The stone fitting to the front continued with the stone panels being checked and ‘snagging’ work carried out. Sections missing where scaffold was tied to the structure were fitted as scaffold came down.
Plastered more of the walls and ceilings in the new Flats.
Walls and ceilings decorated.
Work in the common parts continued with the front entrance being prepared for the stone to the walls and floor. Plastering work was carried out. Common parts decoration continued. Doors fitted.
The fitting of the new Lift continued with the car built inside the shaft. Next week the Lift should be working but being further tested and certified before use, although they have said this for the last 4 weeks. There have been more delays and contractual issues with the Lift company but the Lift is close to be signed off for use. It will be in use by the end of July.
Scaffold to the rear has been removed! There is still some repairs to be made to the new STO and other snagging but at least the scaffold is down.
Gas pipework and AC pipes were fitted at the rear.
More scaffold was removed to the front. Now down to the top of the first floor and Monarflex sheeting removed.. The natural stone can now be seen.
The inside of ther new Flats continued and with second fix items being fitted.
Work to be carried out next week;
Scaffold will continue coming down. It will take around 1 to 2 more weeks, so we can expect all scaffold to be gone by the end of July. There will be further checks as each lift of scaffold is removed. Full cleaning will be carried out, protection from windows removed etc.
The ground floor sections of stone will be fitted after the scaffold has been removed.
Internal work within the new Flats will increase and to include further plastering and fitting of bathrooms. Walls will be closed and plumbing and electrics will advance.
Joinery including kitchens and wardrobes installation to continue. The kitchen for one of the two new Flats was delivered on Thursday and started being fitted. The second kitchen is due this week.
Lift will continue to be fitted.
Air conditioning and ventilation works will continue in the new Flats. External condensers will be fitted in the rear yard.
Second fix electrics will continue and include light fittings and switches.
Work will continue in the common parts with cabling, new pipework and plasterboard being fitted. More plastering will be carried out. The ground floor parts will start. Decoration work will continue.
External decking will continue to be fitted to the new apartments.
Balustrade installation will continue.
More material will be removed from site and more tidying.
We have brought fibre optic into the building and any lessees that wish to sign up should contact either Blenheims or Pirton so it can be arranged. The fibre optic is Hyperoptic.

Front stone looking amazing.